Work continues on pile installation for the new bridge over Lake Pend Oreille. In the coming two months, expect to see continued pile installation, permanent pile bracing installation, and the first pier caps set. The new Bridge Street rail bridge is completed, and no more road closures are planned for this access to City Beach. Steel fabrication for the bridge at Sand Creek is underway in Spokane, WA, and fabrication for precast concrete pier caps and beams is underway at two Knife River locations.
As the summer pool fill up has commenced, access through the Sand Creek channel for boaters will not be impeded. Learn more about our Sand Point Junction Connector Project here.